Temporary Stream Crossing
A temporary stream crossing consists of i) a one-time ford in
flowing waters, ii) a seasonally dry streambed ford, or iii) a
temporary bridge (e.g., Bailey bridge or log stringer bridge).
Temporary stream crossings are employed for short term access
across a watercourse by construction vehicles when an existing
crossing is not available or practical to use. They are not intended
for prolonged use (e.g., forest or mining haul roads). The use of
temporary bridges or dry fording is preferred over fording in
flowing waters due to the reduced risk of damaging the bed and
banks of the watercourse and downstream sedimentation caused
by vehicles. Separate Operational Statements are available for Ice
Bridges and Snow Fills used for temporary access during the
winter and for non-temporary Clear Span Bridges.
The risks to fish and fish habitat associated with temporary
stream crossings include the potential for direct harm to stream
banks and beds, release of excessive sediments and other
deleterious substances (e.g., fuel, oil leaks), loss of riparian
habitat and disruption to sensitive fish life stages.
Fisheries and Oceans Canada (DFO) is responsible for protecting
fish and fish habitat across Canada. Under the Fisheries Act no
one may carry out a work or undertaking that will cause the
harmful alteration, disruption or destruction (HADD) of fish
habitat unless it has been authorized by DFO. By following the
conditions and measures set out below you will be in compliance
with subsection 35(1) of the Fisheries Act.
The purpose of this Operational Statement is to describe the
conditions under which it is applicable to your project and the
measures to incorporate into your project in order to avoid
negative impacts to fish habitat. You may proceed with your
temporary stream crossing project without a DFO review when
you meet the following conditions:
- the project is not located on a Class A stream according
to the Alberta Water Act - Code of Practice,
- the bridge is no greater than one lane in width, and no
part of its structure is placed within the wetted portion of
the stream,
- the work does not include realigning the watercourse,
- for fording in flowing waters and temporary bridges, the
channel width at the crossing site is no greater than 5
metres from ordinary high water mark to ordinary high water
mark (HWM) (see definition below),
- disturbance to riparian vegetation is minimized,
- the work does not involve dredging, infilling, grading or
excavating the bed or bank of the watercourse,
- all crossing materials will be removed prior to the spring
freshet, or immediately following project completion if this
occurs earlier,
- fording involves a one time event (over and back) and will
not occur in areas that are known fish spawning sites,
- the crossing will not result in erosion and sedimentation of
the stream, or alteration (e.g., compaction or rutting) of the
bed and bank substrates,
- the crossing does not involve installation of a temporary
culvert, and
- you incorporate the Measures to Protect Fish and Fish
Habitat when Carrying Out a Temporary Stream Crossing
listed below.
If you cannot meet all of the conditions listed above and cannot
incorporate all of the measures listed below then your project
may result in a violation of subsection 35(1) of the Fisheries Act
and you could be subject to enforcement action. In this case,
you should contact the DFO office in your area if you wish to
obtain DFO’s opinion on the possible options you should
consider to avoid contravention of the Fisheries Act.
You are required to respect all municipal, provincial and
federal legislation that applies to the work being carried out
in relation to this Operational Statement. The activities
undertaken in this Operational Statement must also comply with
the Species at Risk Act (SARA) (www.sararegistry.gc.ca). If you have
questions regarding this Operational Statement, please contact
the DFO office in your area (see Alberta DFO office list).
We ask that you notify DFO, preferably 14 days before starting
your work, by filling out and sending the Alberta Operational
Statement notification form (www.dfo-mpo.gc.ca/regions/
central/habitat/os-eo/provinces-territories-territoires/ab/os-eo20-eng.htm) to the DFO office
in your area. This information is requested in order to evaluate
the effectiveness of the work carried out in relation to this
Operational Statement.
Measures to Protect Fish and Fish Habitat when Carrying Out a Temporary Stream Crossing
- Use existing trails, roads or cut lines wherever possible,
as access routes to avoid disturbance to the riparian
vegetation.
- Locate crossings at straight sections of the stream,
perpendicular to the bank, whenever possible. Avoid
crossing on meander bends, braided streams, alluvial fans,
or any other area that is inherently unstable and may result
in the erosion and scouring of the stream bed.
- While this Operational Statement does not cover the
clearing of riparian vegetation, the removal of select plants
may be necessary to access the construction site. This
removal should be kept to a minimum and within the road
or utility right-of-way or approved work space. When
practicable, prune or top the vegetation instead of
uprooting.
- Generally, there are no restrictions on timing for the
construction of bridge structures or fording seasonally dry
streambeds, as they do not involve in-water work.
However, if there are any activities with the potential to
disrupt sensitive fish life stages (e.g., fording of the
watercourse by machinery) these should adhere to
appropriate fisheries timing widows (see Alberta Water Act
- Code of Practice restricted activity periods, which can be
found at:
http://environment.alberta.ca/1411.html).
- Machinery fording a flowing watercourse to bring
equipment required for construction to the opposite side is
limited to a one-time event (over and back) and is to occur
only if an existing crossing at another location is not
available or practical to use.
- 5.1. If minor rutting is likely to occur, stream bank and bed protection methods (e.g., swamp mats, pads) should be used, provided they do not constrict flows or block fish passage.
- 5.2. Grading of the stream banks for the approaches should not occur.
- 5.3. If the stream bed and banks are steep and highly erodible (e.g., dominated by organic materials and silts) and erosion and degradation are likely to occur as a result of equipment fording, then a temporary bridge should be used in order to protect these areas.
- 5.4. The one-time fording should adhere to fisheries timing windows (see Measure 4).
- 5.5. Fording should occur under low flow conditions, and not when flows are elevated due to local rain events or seasonal flooding.
- Install effective sediment and erosion control measures
before starting work to prevent the entry of sediment into
the watercourse. Inspect them regularly during the course
of construction and make all necessary repairs if any
damage occurs.
- For temporary bridges also employ the following measures:
- 7.1. Use only clean materials (e.g., rock or coarse gravel fill, wood, or steel) for approaches to the bridge (i.e., not sand, clay or organic soil) and install in a manner that avoids erosion and sedimentation.
- 7.2. Design temporary bridges to accommodate any expected high flows of the watercourse during the construction period.
- 7.3. Restore the bank and substrate to pre-construction condition.
- 7.4. Completely remove all materials used in the construction of the temporary bridge from the watercourse following the equipment crossing, and stabilize and re-vegetate the banks.
- Operate machinery in a manner that minimizes disturbance
to the watercourse bed and banks.
- 8.1. Protect entrances at machinery access points (e.g., using swamp mats) and establish single site entry and exit.
- 8.2. Machinery is to arrive on site in a clean condition and is to be maintained free of fluid leaks.
- 8.3. Wash, refuel and service machinery and store fuel and other materials for the machinery away from the water to prevent deleterious substances from entering the water.
- 8.4. Keep an emergency spill kit on site in case of fluid leaks or spills from machinery.
- Stabilize any waste materials removed from the work site,
above the HWM, to prevent them from entering any
watercourse. This could include covering spoil piles with
biodegradable mats or tarps or planting them with
preferably native grass or shrubs.
- Vegetate any disturbed areas by planting and seeding
preferably with native trees, shrubs or grasses and cover
such areas with mulch to prevent soil erosion and to help
seeds germinate. If there is insufficient time remaining in
the growing season, the site should be stabilized (e.g.,
cover exposed areas with erosion control blankets to keep
the soil in place and prevent erosion) and vegetated the
following spring.
- 10.1. Maintain effective sediment and erosion control measures until re-vegetation of disturbed areas is achieved.
Definition:
Ordinary high water mark (HWM) – The usual or average level
to which a body of water rises at its highest point and remains
for sufficient time so as to change the characteristics of the
land. In flowing waters (rivers, streams) this refers to the
“active channel/bank-full level” which is often the 1:2 year flood
flow return level. In inland lakes or wetlands, it refers to those
parts of the water body bed and banks that are frequently
flooded by water so as to leave a mark on the land and where
the natural vegetation changes from predominately aquatic
vegetation to terrestrial vegetation (excepting water tolerant
species). For reservoirs this refers to normal high operating
levels (Full Supply Level).